AD0-E911 practice exam and study guide

Adobe Workfront Project Manager Certified Professional

Timed practice tests for AD0-E911 on the real exam's time limit and blueprint. Every question is original and every option is explained. Your score is broken down by the sections Adobe publishes, so you see what to study next. The question bank holds hundreds of practice questions.

Exam facts

  • Passing score: 33/50 [1]
  • Time limit: 100 minutes [1]
  • Level: Professional [1]
  • Exam fee: $125 (global) / $95 (India) [1]
  • Exam languages (real exam): English [1]
  • Delivery: Online proctored (requires camera access) [1]

Tokens: 1 for $4.99, 5 for $14.99, 10 for $24.99 or 25 for $49.99. One token runs a full timed AD0-E911 practice exam, and every shorter session on that exam is then free. The Unlimited pass is $149.99 for a year of every practice session on every exam.

Get tokens

Exam sections and weights

Adobe publishes these sections and objectives for AD0-E911, quoted here as Adobe words them. [1]

Section 1: Intake and planning, 40% of the exam

  • "Identify different ways to be notified of a work request"
  • "Given a request, review the custom data to determine the appropriate action"
  • "Given a scenario, determine the sharing permissions that are required for an activity"
  • "Given a scenario, determine the appropriate task settings to plan the execution of a task in a specific time frame"
  • "Identify ways to locate key data on a project"
  • "Identify Workfront's functionality to track project risk"
  • "Identify the correct hierarchy of objects in Workfront"
  • "Identify the appropriate field to view a specific assigned resource"
  • "Given a scenario involving a persona during the intake and planning stage, identify the relevant reports and dashboards."

Section 2: Execute, 50% of the exam

  • "Identify ways to understand, apply, and measure of Milestones on a Project"
  • "Given a project, issue, or task, identify whether an approval is in-progress"
  • "Given a scenario, identify the information that date types convey to a project manager"
  • "Given a scenario, determine how different Task Constraints affect the project timeline when used"
  • "Given a scenario, demonstrate how to find project teams and how to notify them of work assignments, updates, or completion of work items"
  • "Given a scenario, describe how to upload a document and generate a proof"
  • "Identify the framework methodologies supported by Workfront"
  • "Given a scenario, determine how to use Workload Balancer within a project to efficiently assign resources"
  • "Given a scenario, locate the specific financial element in Workfront"
  • "Given a Gantt chart, explain the object relationships on the chart"
  • "Compare differences between Condition and Progress Status"
  • "Identify how Workfront teams and Workfront groups can be used"
  • "Given a scenario involving a persona during execution, describe dashboards and reports available and how to build a custom dashboard or report"

Section 3: Closeout, 10% of the exam

  • "Given a particular object status, determine what activities need to be executed or what actions are triggered"
  • "Identify the project elements that can be used to measure project success"

Sample questions

Three questions from the AD0-E911 practice bank, with the answer and why each option is right or wrong.

Question 1

Which Home widget lists the pending requests for every team a user is on, with buttons to assign a request or take it on?

  • A. `My requests`
  • B. `Mentions`
  • C. `Team requests`
  • D. `My approval`

Answer: C. On the Home page, `Team requests` is where a team member picks up work sent to a team. Adobe Workfront groups the pending requests by team and offers buttons to assign one or work on it. [2]

  • A. Wrong. `My requests` offers a filter and a button to rearrange its columns. It has no team grouping and no buttons to assign a request or work on it.
  • B. Wrong. `Mentions` covers recent comments the user made or was tagged in during the past 2 weeks. It carries no request list.
  • C. Right. Adobe Workfront lists pending requests for all of the user's teams in `Team requests`, sorted by team, with buttons to assign a request or work on it.
  • D. Wrong. `My approval` holds pending, assigned, delegated and submitted approvals, with buttons for approval decisions. Team requests are not part of it.

Question 2

The names, descriptions and colors of the milestones in a milestone path that several projects use need checking from a project report that shows the `Milestone Path Name` column. Which step in the report shows all three?

  • A. Hover over the path's name in the `Milestone Path Name` column.
  • B. Click the path's name in the `Milestone Path Name` column.
  • C. Group the report by `Milestone Path Name`.
  • D. Apply the `Milestone` view to the report.

Answer: B. A project report with the `Milestone Path Name` column links each path to its details page, which lists the path's name, ID, description and groups, and the name, description, color and color icon of each milestone. [3]

  • A. Wrong. The path's details open when you click its name in that column, not when you hover over it.
  • B. Right. Clicking a path's name in the `Milestone Path Name` column opens its details page, with the milestone names, descriptions, colors and color icons.
  • C. Wrong. A grouping arranges the report's projects. The milestone names, descriptions and colors are on the path's details page.
  • D. Wrong. Milestone descriptions are not among the information the Milestone view displays for a project.

Question 3

Under which `Completion Mode` can a project manager set a project to a status that equates with Complete by hand?

  • A. Either mode, once the project is Current
  • B. Either mode, once every task and issue is complete
  • C. Manual
  • D. Automatic

Answer: C. `Completion Mode` decides who completes a project. With Manual, the project manager selects Complete once the work is done; with Automatic, Adobe Workfront does it. [4]

  • A. Wrong. Being Current does not open the Complete status to a manual choice. That depends on the Completion Mode being Manual.
  • B. Wrong. Finished tasks and issues are needed before any project completes, but only the Manual mode lets a person select the Complete status.
  • C. Right. A project can be set by hand to a status that equates with Complete only when its Completion Mode is Manual.
  • D. Wrong. With Automatic, Adobe Workfront marks the project Complete itself once its tasks and issues are done, and nobody picks Complete by hand.

Practice for AD0-E911 on ExamSens.ai

ExamSens.ai is not authorized, endorsed or sponsored by Adobe.

References

[1] https://certification.adobe.com/certification/project-manager-certified-professional/1320

[2] https://experienceleague.adobe.com/en/docs/workfront/using/basics/home/use-home-area/get-started-with-home

[3] https://experienceleague.adobe.com/en/docs/workfront/using/administration-and-setup/customize/approvals-milestones/create-milestone-path

[4] https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/manage-projects/change-project-status